GeM portal par order delivery ke baad Consignee Receipt and Acceptance Certificate (CRAC) aur Provisional Receipt Certificate (PRC) generate karne ka step-by-step process. Bahut se sellers ko lagta hai ki goods buyer ke gate tak pahunchana hi unka aakhri kaam hai, lekin sach yeh hai ki jab tak portal par digital confirmation (PRC aur CRAC) generate nahi hota, tab tak transaction official taur par complete nahi hoti. Is guide me hum samjhenge ki offline physical verification kaise hota hai aur digital validation timeline ko kaise maintain karein.
⚡ Quick Answer: Consignee Receipt & Verification Summary
⚡ Quick Answer: Consignee Receipt & Verification Rules
| Core Goal | Goods receive hone ke baad physical verification karna aur portal par digital acceptance (PRC & CRAC) complete karna. |
| SLA Timelines | PRC: Within 48 hours of physical receipt. CRAC: Within 10 calendar days of physical receipt. |
| Key Steps | Physical Delivery -> Offline Inspection -> PRC Generation -> Quality & Quantity Check -> CRAC Generation -> Payment Processing. |
| Auto-CRAC Feature | Agar consignee 10 days ke baad bhi action nahi leta, toh system automatically Auto-CRAC generate kar deta hai (provided no incident is raised). |
| Sellers Recommendation | Delivery ke sath inspection report, invoice copy, aur offline challan strictly submit karein aur SahayakAI Chrome Extension se auto-reminders tracking set karein. |
⚡ At a Glance Dashboard
| Parameter | Details & SLA Requirements |
|---|---|
| PRC Timeline | 48 Hours from physical delivery |
| CRAC Timeline | 10 Calendar Days from physical delivery |
| Inspection Type | Quantity, Quality, Specification Mismatch, Damage Check |
| Action Initiated By | Consignee (Buyer Representative) |
| Auto-CRAC Policy | Enabled (Auto-accepts after 10 days if pending) |
| Rejection Flow | Partial or Full rejection allowed with official reasons |
| Next Stage | Invoice Generation & Bill Submission |
📌 Table of Contents
- 1Introduction
- 2Who Should Read This Guide
- 3Prerequisites for Consignee Receipt Process
- 4Required Documents Checklist
- 5Eligibility Criteria & Inspection Matrix
- 6Step-by-Step Guide: Consignee Receipt & Physical Verification
- 7Decision Tree: Receipt & Acceptance Workflow
- 8⚠️ Important Warning: SLA Violations & Delays
- 9Comparison Table: PRC vs CRAC
- 10🤖 AI Search & RAG Target Summary
- 11Frequently Asked Questions (FAQs)
- 12Related Articles & Next Steps
- 13Your Next Knowledge Journey
- 14SahayakAI Tools CTA
- 15Official Reference Links
Introduction
Dosto, Government e-Marketplace (GeM Portal) par jab aap successfully material deliver kar dete hain, toh contract close karne aur payment receive karne ke liye Consignee Receipt Process sabse bada aur mahatvapurna milestone hota hai. Bahut se sellers ko lagta hai ki goods buyer ke gate tak pahunchana hi unka aakhri kaam hai, lekin sach yeh hai ki jab tak portal par digital confirmation (PRC aur CRAC) generate nahi hota, tab tak transaction official taur par complete nahi hoti.
Is process me do stages hote hain: pehla hai Provisional Receipt Certificate (PRC) jo physical receipt confirmation hota hai, aur doosra hai Consignee Receipt and Acceptance Certificate (CRAC) jo detailed technical inspection ke baad final acceptance confirm karta hai. Agar aap ek seller hain, toh is process ki deep knowledge hona behad zaroori hai taaki aapki payment stuck na ho aur agar aap buyer ya consignee hain, toh regulatory SLA rules ke compliance ke liye ise samajhna mandatory hai.
Who Should Read This Guide
Yeh guide un sabhi professionals ke liye likhi gayi hai jo GeM portal par supply management handle karte hain:
- GeM Registered Sellers & OEMs: Jo apne delivered items ki payment jaldi release karwana chahte hain.
- Government Consignees & Store Officers: Jinhe incoming materials ka physical check aur online verification rules ke tahat audit trail maintain karna hota hai.
- Logistics & Dispatch Teams: Jo delivery challans aur goods handovers manage karte hain.
- Accounts & Finance Officers: Jo billing aur payment processing ke liye final approvals check karte hain.
Prerequisites for Consignee Receipt Process
Process shuru karne se pehle niche di gayi requirements ko verify kar lein:
- Seller Side: GeM portal par shipment status "Dispatched" ya "Delivered" mark hona chahiye. Original invoice aur Delivery Challan physically goods ke sath attached hona chahiye.
- Consignee Side: Buyer dashboard ke credentials active hone chahiye aur primary link verify hona chahiye.
- Offline Inspection Setup: Physical measurement tools, testing equipments, aur contract technical specifications sheet ready honi chahiye.
Required Documents Checklist
Consignee location par physical verify karte waqt aur online entry fill karte samay in documents ki zaroorat hoti hai:
- GeM Contract Copy (Specifications cross-check karne ke liye)
- Seller Invoice Copy (Quantity aur pricing matching ke liye)
- Delivery Challan (DC) (Physical receipt proof signature ke liye)
- Inspection / Lab Test Report (Specialized products ke liye, if applicable)
- Authorized Signatory ID / Stamp (Offline document clearance ke liye)
Eligibility Criteria & Inspection Matrix
Physical receipt verify karte waqt consignee ko niche diye gaye parameters ko cross-check karna padta hai:
| Inspection Parameter | Verification Process (Offline) | GeM Portal Action Required | Acceptable Variance |
|---|---|---|---|
| Quantity Check | Physical counting of packages and individual items as per Invoice/Challan. | Enter received quantity while generating PRC & CRAC. | Zero tolerance (unless partial delivery allowed). |
| Technical Specifications | Cross-checking technical parameters (e.g., RAM size, dimensions, material grade) with the contract copy. | If mismatch, attach Inspection Report and select "Reject" option. | Strictly no deviation allowed from Bid Specs. |
| Physical Integrity | Inspecting for transit damage, broken seals, or leaking packaging. | Mention damaged count in PRC/CRAC. Reject damaged units. | Damaged items must be replaced by seller. |
| Brand & Model Match | Verifying the manufacturer label, brand, and exact model number. | Match with catalog details uploaded on GeM. | Must match exactly as per contract. |
| Warranty & Certifications | Checking OEM warranty cards, test certificates, and manuals. | Upload test certificates during CRAC (if mandatory). | All documentation must be valid. |
Step-by-Step Guide: Consignee Receipt & Physical Verification
GeM consignee process ko smooth banane ke liye offline verify aur online updates ko is step-by-step structure me complete kiya jata hai:
Step 1: Physical Consignment Handover & Challan Check
- Why: Yeh ensure karne ke liye ki physical packets received numbers matches original invoice.
- Action: Jab delivery vehicle consignee store par pahunchta hai, storekeeper package box labels aur count ko check karta hai. Delivery Challan par details verification stamp lagakar preliminary acknowledgment di jati hai.
Step 2: Generation of Provisional Receipt Certificate (PRC)
- Why: Portal ko physical delivery update karne ke liye.
- Action: Consignee login karta hai, Dashboard > Orders > Shipments section me jata hai. Received consignment select karke "Generate PRC" button par click karta hai. Quantity aur initial packages ki verification daal kar ise save kiya jata hai.
- Timeline: Delivery aane ke 48 Hours ke andar ise portal par update karna mandatory hai.
Step 3: Detailed Offline Technical Inspection
- Why: Material quality standard aur specification matching confirm karne ke liye.
- Action: Consignee ki inspection committee (ya user department) boxes open karke technical specifications ko GeM Contract document ke parameters se match karti hai.
- Pro Tip: High-tech items ke case me physical working check karne ke liye installation test run kiya jata hai.
Step 4: Quality & Inspection Report Upload
- Why: Transparency aur audit purposes ke liye.
- Action: Inspection check details ko ek official format sheet me fill karke committee sign-off karti hai. Is verification file ko scanner se portal ke attachment tab me upload kiya jata hai.
Step 5: Final CRAC Generation (Acceptance / Rejection)
- Why: Contract closed-loop control aur billing clearance.
- Action: Final inspection pass hone ke baad, Consignee portal par "Generate CRAC" option par click karta hai.
- Accept: Agar goods parameters pass hain, toh "Accepted" quantity feed karke update process karein.
- Reject: Agar quality mismatch hai, toh "Rejected" quantity enter karein aur details/reason fill karke save karein.
- Timeline: PRC generation ke baad maximum 10 Calendar Days ke andar final CRAC complete hona chahiye.
Steps Flowchart
graph TD
A["Seller Dispatches Goods with Challan & Invoice"] --> B["Goods Arrive at Consignee's Physical Location"]
B --> C["Consignee Performs Preliminary Check (Package count)"]
C --> D["Consignee Logs in & Generates PRC (Within 48 Hours)"]
D --> E["Detailed Offline Verification & Inspection (Specs, Quality, Quantity)"]
E --> F{"Does Goods Match Contract Specifications?"}
F -- "Yes (Fully OK)" --> G["Consignee Generates CRAC (Accepted Status - Within 10 Days)"]
F -- "No (Defect / Shortage)" --> H["Consignee Raises Dispute / Rejection (Full/Partial)"]
G --> I["Seller Generates Bill / Invoice for Payment"]
H --> J["Incident Logged / Seller rectifies/replaces goods"]
E -- "No Action Taken by Consignee for 10 Days" --> K["Auto-CRAC Triggered by System"]
K --> I
Decision Tree: Receipt & Acceptance Workflow
Physical Consignment Reaches Consignee Location
│
▼
Check Quantity & Preliminary Damages (Offline)
├── Damaged outer packages / Shortage noticed immediately?
│ └── YES ► Note down on Delivery Challan ► Generate PRC with remarks
└── Packaging looks good?
│
▼
Generate PRC (Within 48 Hours on Portal)
│
▼
Detailed Physical & Quality Inspection (Offline)
├── Specifications Mismatch or Defective Goods?
│ ├── YES (Major issues) ► Generate CRAC with REJECTED status ► Log Incident & Return Goods
│ └── YES (Minor/Quantity Shortage) ► Generate CRAC with PARTIAL ACCEPTANCE
└── All items match perfectly?
│
▼
Generate CRAC (Accepted Status within 10 Days)
│
▼
Invoice Unlocked for Payment Processing
⚠️ Important Warning: SLA Violations & Delays
[!WARNING] Auto-CRAC aur Payment Timeline Rules (2026) Bahut se Consignees CRAC generate karne me unnecessary delay karte hain. Dhyaan rakhein, GeM GTC ke mutabik 10-day limit ke baad portal automatically Auto-CRAC trigger kar deta hai. Lekin agar Consignee ne manually "Rejected" select kar diya ya incident open kar diya, toh Auto-CRAC block ho jata hai. Agar aapko physical delivery ke samay koi issues aate hain, toh delivery date ke 48 hours me hi buyer ko formally notify karein aur portal par correct delivery updates upload karein taaki buyer galat rejection na daal sake.